Hai Kun submarine conducts fresh sea trials after month-long wait

2026-11-26
Focus Taiwan
分享
分享至Facebook 分享至Line 分享至X
The Hai Kun submarine departs from the Port of Kaohsiung on Tuesday morning for its latest round of sea trials. CNA photo Nov. 24, 2026
The Hai Kun submarine departs from the Port of Kaohsiung on Tuesday morning for its latest round of sea trials. CNA photo Nov. 24, 2026

Kaohsiung, Nov. 24 (CNA) Taiwan's first domestically built submarine, the Hai Kun (Narwhal), departed from the Port of Kaohsiung on Tuesday morning for its latest round of sea trials, including submerged tests, nearly a month after its previous trial.

Public records showed that Tuesday's trial marked the submarine's 26th sea trial overall and its 20th submerged-navigation test. The previous sea trial was conducted on Oct. 15.

Military expert Chi Tung-yun (紀東昀) told reporters that the latest round of tests was expected to revisit previously completed test items while also covering new ones to verify the stability of the submarine's systems.

He said he believed much of the past month had been spent allowing technicians from the original manufacturers of components used in the submarine to travel to Taiwan to provide technical support.

This also highlights the urgent need to localize and indigenize submarine subsystems in the future, he said.

Chi added that, based on the experiences and practices of other countries, a submarine does not have to be perfect before it can be delivered to the Navy, as long as any components needing further work do not compromise the vessel's overall navigational safety or operational capabilities.

He therefore estimated that the Hai Kun could be delivered to the military as early as the end of this year or January next year.

Defense Minister Wellington Koo (顧立雄) has repeatedly stressed that the testing will proceed according to established procedures, with safety and quality taking precedence over any predetermined delivery deadline.